In short
Client Leegwater Wood Treatment B.V.
The assignmentDue to company growth, a new storage facility is required to continue operations at Leegwater Houtbereiding B.V. It is important that this is created on the current site and that the tent is high enough to store and transport stacks of wood with a forklift.
Situation
Leegwater Houtbereiding B.V. keeps the natural enemies of wood at bay sustainably outdoors through impregnating, drying, coating, and fireproofing.ย
Result / solution
Door de enorme groei van het bedrijf was een extra Storage space necessary for the wood. The wood had to be stored in a safe and dry space. Kontent Structures a custom tent pavilion has been erected for this. The tent measures 30 x 30m with a wall height of 4m and had to be installed under the 125 kV high-voltage network. The tent was erected within a few days and also has an overhead door at the front that can be locked when necessary.
View all other items here structures.ย